Japan halts Tepco plan to restart key nuclear plant after safety breaches By Reuters
By Aaron Sheldrick and Yuka Obayashi
TOKYO (Reuters) – Japan’s nuclear regulator said on Wednesday that it would bar
Tokyo Electric Power Co (Tepco), operator of the wrecked Fukushima Daiichi nuclear plant, from restarting its only operable atomic power station due to safety breaches uncovered last year.
The setback marks another low point for a company that was at the heart of Japan’s nuclear industry but has struggled to reform its safety culture after years of lax compliance even before its widely criticized response to the Fukushima disaster of 2011.
Tepco had been hoping to restart the Kashiwazaki-Kariwa station, the world’s biggest atomic power plant with capacity of 8,212 megawatts, in a quest to slash the utility’s operating costs by more than $800 million a year.
Asked for a response to the stance taken by the Nuclear Regulation Authority (NRA), Tepco told Reuters it would “engage in drastic reforms.”
The company suffered a barrage of criticism in March when the failings at the Kashiwazaki-Kariwa plant came to light, including security mis-steps that led to an unauthorised staff member accessing sensitive areas of the plant.
Japan’s industry minister said at the time the plant would not be restarted any time soon, as regulators slammed the breaches, which included failure to protect nuclear materials.
The NRA on Wednesday issued a corrective action order addressed to Tepco, preventing it from transporting new uranium fuel to Kashiwazaki-Kariwa or loading fuel rods into its reactors – effectively stopping it from restarting them.
The step is the first time the NRA has ordered such action since it was established in 2012 as a new agency following regulatory failings that emerged during the Fukushima disaster.
Tepco told Reuters that it “understands the gravity of this situation and is taking the order issued by the Nuclear Regulation Authority very seriously.”
Its shares closed more than 3% lower in Tokyo, while the broader market was down around 0.4%.
In accordance with Wednesday’s move by the watchdog, Tepco must submit a report to the NRA by Sept. 23 detailing improvements in handling nuclear materials. The NRA will assess these before removing the corrective order, the watchdog has said, a process that could take at least a year.
Tepco has said it can save 90 billion yen ($827 million) in fuel costs annually by getting reactors number 6 and 7 at Kashiwazaki-Kariwa restarted.
The 1,356 megawatt units have been off-line since at least 2012 and are the only ones at the station that have received basic preliminary licenses to operate.
($1 = 108.8500 yen)